Drinking water container Wachhecken






Project Information
On behalf of Stadtwerke Taunusstein, we carried out the renovation of two water chambers, each with a volume of 350 m³, between 2020 and 2021. The work on the 970 m² area included preparatory granulate blasting and demolition work as well as specialised PCB remediation. After the concrete renovation of the interior surfaces of the tanks, a new mineral-based coating was applied, with the ceilings in white, the walls in blue and the floors in grey. In addition, the pipework and the installation of the technical equipment were carried out professionally.
Client
Taunusstein municipal utilities
Project size
2 water chambers, volume 350 m³ each
Implementation
2020 – 2021
Scope of services/project description
970 m²
- Granulate blasting and demolition work
- PCB remediation
- Concrete renovation of the inner surfaces of the water chambers
- Purely mineral recoating of the interior surfaces of the water chamber (blue wall, white ceiling, grey floor)
- pipework
- Technical equipment