Interior renovation of HB South Left Chamber

Project Information

On behalf of ZVG Dieburg, the interior renovation of the left chamber of the south elevated tank was carried out between October 2019 and March 2020. The project covered a total area of 900 m² of ceiling space, 900 m² of floor space, 750 m² of wall space and 150 m² of support space. The scope of services included the establishment of a hygiene protection zone and comprehensive protective measures, substrate pre-treatment and professional concrete repair. Finally, the interior coating and the necessary technical installations were carried out.

Client
ZVG Dieburg

project size

  • 900 m² ceiling area
  • 900 m² floor space
  • 150 m² of column space,
  • 750 m² wall space
 

Implementation
October 2019 – March 2020

Scope of services/project description

  • hygiene protection zone
  • protective measures,
  • substrate preparation
  • concrete repair
  • inner coating
  • technical installation