Underground parking garage
Bleichstr. Wiesbadener Volksbank








Project informationen
On behalf of Wiesbadener Volksbank, the underground car park on Bleichstraße was comprehensively refurbished. As general contractor, we coordinated and carried out a wide range of works, including structural and civil engineering works, concrete repair and coating as well as drainage, electrical and paving works.
The refurbishment included approximately 800 m² of floor area with an OS 14 coating system, 1,200 m² of wall and ceiling surfaces with an OS 4 system, and 800 m² of PCC screed. In addition, approximately 900 m² of paving was completed, 100 m of underground drainage pipes were renewed, and around 50 m³ of concrete works were carried out.
The central location of the project in the heart of Wiesbaden presented particular logistical challenges. The necessary removal work was carried out by Wannenwetsch HDW GmbH.
Client
Wiesbadener Volksbank
Project size
- 800m² – OS 14
- 800m² – PCC screed
- 900m² – Paving
- 1200m² – OS 4
- 100m – utility lines replaced
- 50m³ – concrete work / structural work
Implementation
November 2025 – August 2026
Scope of services/ description
General contractor
- Structural work
- Coating
- Civil engineering
- Entwässerung
- Elektrik
- Pflasterarbeiten
- Betoninstandsetzung
Special features
Lage des Projekts in mitten der „Baustellenhauptstadt“ Wiesbaden. Hohe logistische Herausforderungen.