Digester tank 2 – Wastewater treatment plant, Ingolstadt, Germany

Project information

On behalf of the Ingolstadt Central Sewage Treatment Plant Association, the renovation of digestion tank 2 was carried out in June 2020. Covering an area of 50 m², the work initially involved preparing the substrate and increasing the concrete cover by 25 mm using a highly sulfate-resistant mineral material from MC-Bauchemie. An ECC fine filler was then applied and the repair was professionally completed with a duroelastic coating system, also from MC-Bauchemie.

Client
Ingolstadt Central Sewage Treatment Plant Association

Project size
50 m2

Implementation
June 2020

Scope of services/project description

  • Surface preparation
  • Increase in concrete cover by 25 mm using a highly sulfate-resistant mineral material from MC-Bauchemie
  • Applying an ECC fine filler
  • Application of a duroelastic coating system from MC-Bauchemie