Digester tank 2 – Wastewater treatment plant, Ingolstadt, Germany




Project information
On behalf of the Ingolstadt Central Sewage Treatment Plant Association, the renovation of digestion tank 2 was carried out in June 2020. Covering an area of 50 m², the work initially involved preparing the substrate and increasing the concrete cover by 25 mm using a highly sulfate-resistant mineral material from MC-Bauchemie. An ECC fine filler was then applied and the repair was professionally completed with a duroelastic coating system, also from MC-Bauchemie.
Client
Ingolstadt Central Sewage Treatment Plant Association
Project size
50 m2
Implementation
June 2020
Scope of services/project description
- Surface preparation
- Increase in concrete cover by 25 mm using a highly sulfate-resistant mineral material from MC-Bauchemie
- Applying an ECC fine filler
- Application of a duroelastic coating system from MC-Bauchemie