Renovation of the Königsberger Straße elevated tank

Project Information

Between May and November 2022, we carried out a comprehensive renovation of a circular water chamber with a capacity of 1,500 m³ for Stadtwerke Bad Nauheim GmbH. The work began with the removal of 800 m² of wall, pillar and floor tiles, followed by the preparation of the substrate over a total area of 1,140 m². This was followed by the application of a new cement-bound coating to the interior surfaces, with 345 m² of ceiling space finished in white, 440 m² of wall and column surfaces in blue and 345 m² of floor space in grey, all professionally executed.

Client

Bad Nauheim Municipal Utilities Ltd.

Project size
Circular water chamber with a volume of 1,500 m³

Execution

May 2022 – November 2022

Scope of services/project description

  • 800 m² – demolition of wall/pillar/floor tiles

  • 1,140 m² – Substrate preparation

  • 345 m² – Cement-bound coating ceiling (white)

  • 440 m² – Cement-bound coating on walls and columns (blue)

  • 345m² – Cement-bound floor coating (grey)