Sports hall Feldbergschule, Mainz, Germany








Project information
On behalf of the city of Mainz (Mainz Building Management), the energy-efficient renovation of the sports hall at Feldberg School in Mainz was carried out in spring 2022. The project covered an exterior facade area of 1,250 m² and 328 m² of ceiling area.
The scope of services included the installation of a composite thermal insulation system (ETICS) using mineral wool insulation boards with a thickness of between 140 mm and 300 mm. The system was applied directly to the concrete facade and finished with a 2 mm thick textured plaster coating as the final surface protection.
Client
City of Mainz, Mainz Building Management
Project size
ETICS exterior facade 1,250 m² and ceiling 328 m²
Completion
Spring 2022
Scope of services/project description
- ETICS, mineral wool insulation boards
- Insulation thickness from 140 mm to 300 mm
- ETICS on concrete facade with subsequent 2 mm pane protection as surface structure