From April 2025 to June 2026, we carried out ETICS works on approximately 3,600 m² of facade area at the new Dieburg Tax Office building.
The scope of work included the installation of an external thermal insulation composite system (ETICS) with 200 mm EPS insulation. A special feature is the 5 mm MineralAktiv finishing render by Knauf, which was used on a building in Germany for the first time as part of this project.
Further special features include columns with a brushed finish and JOMA external venetian blind boxes integrated into the ETICS.
Client
Biskupek/Scheinert GbR
Project size
~ 3.600 m² of facade area
Implementation
April 2025- June 2026
Umfang der Leistung/Projektbeschreibung
- ETICS with 200 mm EPS insulation
- Approx. 3,600 m² of facade area
- 5 mm MineralAktiv finishing render / SM700 Pro
Special features
- 5 mm MineralAktiv finishing render by Knauf on the main facade area – used on a building in Germany for the first time
- Columns with a brushed finish
- JOMA external venetian blind boxes integrated into the ETICS