A60/643 motorway junction, Mainz, Germany




Project information
On behalf of the Montabaur Motorway Authority, the complete renovation of two bridge structures at the A60/643 motorway junction in Mainz was carried out between July 2017 and October 2018. The project comprised two structures, each 27 meters long, which underwent comprehensive repair work from above. The services included the renewal of the caps and guard rails as well as the roadway over a distance of approximately 100 meters in front of and behind the bridges. In addition, the undersides of the bridges were professionally concreted.
Client
State Mobility Agency, Montabaur Motorway Authority (LBM)
Project size
Complete renovation of two bridge structures, each 27 m long
Implementation
July 2017 – October 2018
Scope of services/project description
- Complete performance from above
- Renewal of the caps
- Renovation of the roadway approx. 100 m before and after the bridge
- Renewal of guardrails
- Concreting the undersides of bridges