Schrägstielrahmenbrücken, Frankfurt, Germany








Project information
On behalf of the Frankfurt am Main Office for Road Construction and Development, three inclined strut bridges, each 110 meters long, were repaired between August 2019 and March 2020. The renovation of the pedestrian bridges included the removal of the asphalt pavement, the waterproofing, and the side upstands and railings. This was followed by concrete repair work on the entire structure and the installation of new waterproofing. The work was completed by concreting new upstands, installing mastic asphalt, and fitting new railings.
Client
Office for Road Construction and Development, Frankfurt am Main
Project size
3 pedestrian bridges, each 110 m long
Implementation
August 2019 – March 2020
Scope of services/project description
- Repair of three inclined-leg frame bridges (pedestrian bridges)
- Removal of asphalt pavement and waterproofing
- Removal of the side upstand
- Demolition of the railing
- Concrete repair on the entire structure
- Production of a seal
- Concreting of the new side upstand
- Installation of mastic asphalt
- Installation of a new railing